Robotics ground controllers in NASA’s Mission Control Center at the agency’s Johnson Space Center in Houston successfully replaced a failed Main Bus Switching Unit (MBSU) on the International Space Station with a spare using robotic operations on Thursday, May 2. The operation to replace the failed unit was conducted using the station’s Canadarm2 and Dextre, both part of Canada’s contribution to the International Space Station.
Using complex robotic work to perform critical maintenance allows astronauts to spend more time working on scientific experiments and helps develop better technologies and procedures for future human and robotic exploration beyond low-Earth orbit.
“Developing new robotic systems is extremely important to get our astronauts back to the Moon by 2024,” Robotics Operations Systems Officer Mike Ferullo said. “The techniques and methods that we are developing with Dextre and Canadarm2 are directly applicable to future missions, and the construction and repair of any Moon-based mission will be done with robotics wherever possible. It’s an extremely exciting time to be involved in space robotics.
Dextre is a versatile robot used to perform routine maintenance on the station. Equipped with lights, video equipment, a tool platform, and four tool holders, Dextre’s dual-arm design and precise handling capabilities reduces the need for spacewalks to conduct maintenance outside the orbiting laboratory.
The Canadarm2 serves as the station’s robotic arm. It’s used to move supplies, equipment, Dextre and even astronauts. The robotic arm is also used to capture visiting spacecraft and attach them to the station.
The completion of the robotics work was the second time an MBSU was swapped out without the need for a spacewalk.
“Previous replacements allowed us to review different arm configurations and the force with which we pulled the unit out,” Ferullo said. “Every operation we do gives us a better understanding about how to move forward with future repairs and the support of payloads.”
The failure on April 29 of the station’s MBSU-3, one of four power distributors on the station’s backbone truss structure, reduced the station’s power supply by nearly 25 percent. Following the failure, the station crew installed a series of jumpers in the station’s Unity connecting module (Node 1) to reroute power to experiments and hardware and ensure limited impact to continued station operations.
“Installing the power jumpers allowed the recovery of several critical pieces of equipment,” Power and Thermal Flight Controller Jay Boucher said. “Even though the jumpers helped continue station operations, replacing the failed unit would be required to regain the redundant power supply required for the US robotic arm to capture SpaceX’s Dragon cargo spacecraft that was scheduled to launch.”
Dragon launched successfully on May 4 and was captured and installed on the Earth-facing side of the station two days later to deliver more than 5,500 pounds of research, crew supplies, and hardware to the International Space Station.
Source: Mark Garcia, MORI Associates
Testimonial
"We’re proud to call I-Connect007 a trusted partner. Their innovative approach and industry insight made our podcast collaboration a success by connecting us with the right audience and delivering real results."
Julia McCaffrey - NCAB GroupSuggested Items
TI’s New Power-management Solutions Enable Scalable AI Infrastructures
10/14/2025 | Texas InstrumentsTexas Instruments (TI) debuted new design resources and power-management chips to help companies meet growing artificial intelligence (AI) computing demands and scale power-management architectures from 12V to 48V to 800 VDC.
Analog Devices Launches ADI Power Studio™ and New Web-Based Tools
10/14/2025 | Analog Devices, Inc.Analog Devices, Inc., a global semiconductor leader, announced the launch of ADI Power Studio, a comprehensive family of products that offers advanced modeling, component recommendations and efficiency analysis with simulation. In addition, ADI is introducing early versions of two new web-based tools with a modernized user experience under the Power Studio umbrella:
SEMICON West: The Path to a $1 Trillion Future
10/14/2025 | Marcy LaRont, I-Connect007After more than 50 years in San Francisco, SEMICON West moved its 2025 show to Phoenix, which is significant because it highlights the importance of Arizona as a semiconductor and tech hub. Though the show will be back in San Francisco in 2026, the overwhelmingly warm welcome SEMI received from Arizona Governor Katie Hobbs, Phoenix Mayor Kate Gallego, and ASU President Michael Crowe—who has been responsible for ASU repeatedly achieving the U.S. News and World Reports most innovative university ranking—was remarked upon repeatedly. All indications are that SEMICON West may well be back in Phoenix after that 2026 season.
Flex Announces New AI Infrastructure Platform to Speed Deployment by Up to 30%
10/13/2025 | FlexFlex announced the industry's first globally manufactured, fully integrated platform designed for gigawatt data centers supporting AI and HPC.
Imec Launches 300mm GaN Program to Develop Advanced Power Devices and Reduce Manufacturing Costs
10/13/2025 | ImecImec, a world-leading research and innovation hub in nanoelectronics and digital technologies, welcomes AIXTRON, GlobalFoundries, KLA Corporation, Synopsys, and Veeco as first partners in its 300mm gallium-nitride (GaN) open innovation program track for low- and high-voltage power electronics applications.