August 29, 2019 | Brookhaven National LaboratoryEstimated reading time: 6 minutes
“We made sure to automate as much of the production facility as possible,” O’Connor said. “Testing a single raft could take up to three days. We were working on a tight schedule, so we had our automated facility running 24/7. Of course, out of a concern for safety, we always had someone monitoring the facility throughout the day and night.”
Constructing the complex sensor array, which operates in a vacuum and must be cooled to -100° Celsius, is a challenge on its own. But the Brookhaven team was also tasked with testing each fully assembled raft, as well as individual sensors and electronics. Once each raft was complete, it needed to be carefully packaged in a protective environment to be safely shipped across the country to SLAC.
The LSST team at Brookhaven completed the first raft in 2017. But soon after, they were presented with a new challenge.
“We later discovered that design features inadvertently led to the possibility that electrical wires in the rafts could get shorted out,” O’Connor said. “The rate at which this effect was impacting the rafts was only on the order of 0.2%, but to avoid any possibility of degradation, we went through the trouble of refitting almost every raft.”
Now, just two years after the start of raft production, the team has successfully built and shipped the final raft to SLAC for integration into the camera. This marks the end of a 16-year project at Brookhaven, which will be followed by many years of astronomical observation.
Many of the talented team members recruited to Brookhaven for the LSST project were young engineers and technicians hired right out of graduate school. Now, they’ve all been assigned to ongoing physics projects at the Lab, such as upgrading the PHENIX detector at the Relativistic Heavy Ion Collider—a DOE Office of Science User Facility for nuclear physics research—to sPHENIX, as well as ongoing work with the ATLAS detector at CERN’s Large Hadron Collider. Brookhaven is the U.S. host laboratory for the ATLAS collaboration.
“Brookhaven’s role in the LSST camera project afforded new and exciting opportunities for engineers, technicians, and scientists in electro-optics, where very demanding specifications must be met,” Wahl said. “The multi-disciplined team we assembled did an excellent job achieving design objectives and I am proud of our time together. Watching junior engineers and scientists grow into very capable team members was extremely rewarding.”
Brookhaven Lab will continue to play a strong role in LSST going forward. As the telescope undergoes its commissioning phase, Brookhaven scientists will serve as experts on the digital sensor array in the camera. They will also provide support during LSST’s operations, which are projected to begin in 2022.
SLAC National Accelerator Laboratory installs the first of Brookhaven's 21 rafts that make up LSST's digital sensor array. Photo courtesy SLAC National Accelerator Laboratory.
“The commissioning of such a complex camera will be an exciting and challenging endeavor,” said Brookhaven physicist Andrei Nomerotski, who is leading Brookhaven’s contributions to the commissioning and operation phases of the LSST project. “After years of using artificial signal sources for the sensor characterization, we are looking forward to seeing real stars and galaxies in the LSST CCDs.”
Once operational in the Andes Mountains, LSST will serve nearly every subset of the astrophysics community. Perhaps most importantly, LSST will enable scientists to investigate dark energy and dark matter—two puzzles that have baffled physicists for decades. It is also estimated that LSST will find millions of asteroids in our solar system, in addition to offering new information about the creation of our galaxy. The images captured by LSST will be made available to physicists and astronomers in the U.S. and Chile immediately, making LSST one of the most advanced and accessible cosmology experiments ever created. Over time, the data will be made available to the public worldwide.
Brookhaven National Laboratory is supported by the U.S. Department of Energy’s Office of Science. The Office of Science is the single largest supporter of basic research in the physical sciences in the United States and is working to address some of the most pressing challenges of our time.
Page 2 of 2Suggested Items
SIA Praises Finalization of CHIPS Incentives to Supplement SK Hynix’s $3.87 Billion Investment in Indiana
12/20/2024 | SIAThe Semiconductor Industry Association (SIA) today released the following statement from SIA President and CEO John Neuffer commending finalization of CHIPS and Science Act manufacturing investments announced by the U.S. Department of Commerce and SK hynix. The incentives will supplement the company’s $3.87 billion investment in Indiana for advanced packaging operations and R&D.
SIA Commends Finalization of CHIPS Incentives for GlobalWafers
12/19/2024 | SIAThe Semiconductor Industry Association (SIA) released the following statement from SIA President and CEO John Neuffer commending finalization of CHIPS and Science Act manufacturing investments announced by the U.S. Department of Commerce and GlobalWafers. The incentives will support the development of semiconductor wafer production in Texas and Missouri.
Statistically Testing Inner Layer Yield Improvement Projects
12/18/2024 | Dr. Patrick Valentine, UyemuraCan we trust our measurement system to give us reliable data? Is it accurate, repeatable, and reproducible? Measurement is the foundation of quality. We measure for two primary reasons: to make decisions on product quality and to provide data that will inform continuous improvement projects. We can engage in continuous improvement projects if we are confident in our measurement systems.
PCB Fabricator Cistelaier Receives ESA Qualification
12/16/2024 | CistelaierThe capability and independence of its space industry are strategic for Europe, and the European Space Community needs a qualified, resilient supply chain with adequate production capacity. Specifically, it requires greater production capacity in PCB manufacturing. On this premise, in early 2020, Cistelaier began the process of obtaining an ESA qualification.
INVISIO, U.S. Defense Innovation Unit (DIU) Advancing Wireless Tactical Communications Through Customer Collaboration
12/09/2024 | INVISIOA cooperation between INVISIO and the U.S. Defense Innovation Unit (DIU) has showcased the benefits of co-development when it comes to developing tactical communications solutions for military operators at speed, resulting in the INVISIO Link™ solution.