Raytheon's Development and Testing on Track for DDG 51 Flight III
January 18, 2016 | Raytheon CompanyEstimated reading time: 2 minutes
Raytheon Company announced its AN/SPY-6(V) Air and Missile Defense Radar (AMDR)team has completed the first full radar array, fully populated with component Line Replaceable Units (LRUs), including more than 5,000 Transmit/Receive elements, in 140 days. In less than two years, the radar has been designed, built and transitioned to test; the Engineering and Manufacturing Development (EMD) phase of the program is now more than 66 percent complete. The program remains on track to begin production and deliver on time to the FY16 authorized DDG 51 Flight III destroyer.
"As each milestone is completed, development of the SPY-6 radar progresses on schedule," said U.S. Navy Captain Seiko Okano, major program manager, Above Water Sensors (IWS 2.0). "With this array, now built and operational in the Near Field Range, we're proceeding to plan and commencing full-scale integration and test of AMDR's unprecedented capability."
Subcontractor Major Tool and Machine delivered the array structure to Raytheon's Near Field Range on July 29; and Raytheon installed all passive RF components before September 1. The first Radar Modular Assembly (RMA) was powered up in October and testing began. All RMA chassis were installed by October 16, complete with cooling, power, fiber-optic control and data interfaces. In 79 days the array infrastructure was complete – verification of the simplicity of the AMDR array design. Population of the array with Transmit Receive Integrated Multi-channel Modules and Distributed Receiver/Exciter LRUs completed on December 16.
These recent achievements are among the many successes and milestones realized to date, including:
- Nine of nine major program milestones completed on schedule, including hardware and software Critical Design Reviews and the Development Test Event 2 (DT-2) Readiness Review
- Transition to DT-2 - currently in process, culminating in 2016 with verification of hardware level specifications to requirements and shipment of the array to the Pacific Missile Range Facility in Hawaii for system validation testing (DT-3)
- Completed Build 2 software early, with all planned functionality (30 capabilities), formally qualified in July 2016; Build 3 is more than 75% percent complete
- 95% of EMD hardware production is complete; awaiting final power systems delivery in early 2016
Page 1 of 2
Suggested Items
Target Condition: From Dream House to Drill Files
06/05/2025 | Kelly Dack -- Column: Target ConditionIf you caught the movie “Barbie,” you may have laughed at its over-the-top utopia where every day begins with perfect weather, perfect smiles, and a perfectly pink commute. But beyond the plastic glam, the film subtly critiques the illusion of perfection—a message that feels surprisingly relevant to the world of PCB design and manufacturing.
Datest Receives Its 16th AS9100D Recertification Audit
06/03/2025 | DatestDatest, a trusted leader in advanced testing, engineering, inspection, and failure analysis services, proudly announces sixteen straight years of aerospace-grade perfection. Cue the confetti cannons (ESD-safe, of course).
The Chemical Connection: Reducing Defects in Circuit Board Production
06/04/2025 | Don Ball -- Column: The Chemical ConnectionWe all agree that in any manufacturing process, reducing defects in your product induced during manufacture (aka increasing yields) is a good thing. Doing so, however, can be a source of contention and frustration. I don’t pretend to be an expert in this field, because most of my work involves feasibility studies for new concepts or testing improvements made to existing equipment. High yields were usually not a factor; it’s simply about having enough data to prove or disprove a concept or seeing whether improvements to equipment design actually work. However, here are some observations I made visiting quality shops where high production at high yields was important.
atg Luther Maelzer Announces Grand Opening of New Office and Manufacturing Facility
06/02/2025 | atg Luther & Maelzer GmbHAtg Luther Maelzer, a leading supplier of electrical testing solutions for the PCB industry, recently celebrated with a grand opening of their new office and manufacturing facility in Wertheim, Germany.
It’s Only Common Sense: Trust Is All You Need
06/02/2025 | Dan Beaulieu -- Column: It's Only Common SenseTrust is all you need, and the best way to build it is by showing that others have placed their faith in you. This is where social proof becomes a game-changer. Social proof is a psychological phenomenon that influences people to follow others’ actions, especially in uncertain situations. By leveraging social proof, businesses can attract customers and close deals more efficiently. Here’s how to incorporate social proof into your strategy and watch your closing rate soar.