Toyota Announces Adjustments to Domestic Production
April 15, 2020 | Toyota Motor Corp.Estimated reading time: 1 minute
Due to the effects of COVID-19 on the current market and the decline in demand of new vehicles globally, Toyota intends to make gradual adjustments in production operations at all plants for completed vehicles in Japan, starting from May 1.
Specifically, we have decided to halt production for two days, on May 1 and 11, and plan to reflect the operation days on alternative dates. Additionally, we plan to add non-operating days as well as reducing operation time from double shifts to a single shift from May 12 for some of the plants and production lines producing vehicles for overseas markets.
We sincerely apologize for the inconvenience caused to our suppliers and people in those regions.
Please refer to the below for more details.
Production suspension for nine production lines at five plants (Among a total of 28 production lines at 15 plants)
- Tsutsumi Plant, production lines #1 and #2
4 operating days from May 12 (Tue) to 15 (Fri) - Tahara Plant, production line #1
5 operating days from May 12 (Tue) to 18 (Mon) - Toyota Motor East Japan, Inc. (TMEJ), production lines F201 and F301 at Higashi-Fuji Plant
1 operating day on May 12 (Tue) - Toyota Motor East Japan, Inc. (TMEJ), production line #1 at Iwate Plant,
2 operating days for May 12 (Tue) and 13 (Wed) - Hino, Hamura Plant, production line #1
4 operating days from May 12 (Tue) to 15 (Fri) - Hino, Hamura Plant, production lines #2 and #4
1 operating day on May 12 (Tue)
Reduction of operation to a single shift in four production lines at three plants
Tahara Plant, production lines #1 and #3
- Operation with a single shift from May to June (Employees to continue working double shifts)
- Hino, Hamura Plant, production line #1
Operation with a single shift from May to June (No second shift) - Gifu Auto Body Co., Ltd., production line #2
Operation with a single shift from May to June (No second shift)
In addition, since we anticipate that the delivery of some parts from overseas will be affected due to COVID-19, we will halt production for three operating days between April 20 (Mon) and 22 (Wed) for Takaoka Plant production line #2 and Toyota Industries Corporation production lines #301 and #302.
Note that operation plans may change in accordance with changes in demand and the situation of parts delivery, going forward.
Suggested Items
Kitron Receives EUR 4 Million Contract for Defense Airborne Radar Application
07/02/2025 | KitronKitron has received an order valued at EUR 4 million to produce electronics modules for airborne radar application, destined for the US market.
Toni Patzner Becomes Global Head of Supply Chain Management at ASMPT SMT Solutions
07/01/2025 | ASMPTOn June 1, 2025, Toni Patzner assumed the position of Global Head of Supply Chain Management. The experienced manager succeeded Jörg Cwojdzinski, who retired after decades of service.
Driving Innovation: Direct Imaging vs. Conventional Exposure
07/01/2025 | Simon Khesin -- Column: Driving InnovationMy first camera used Kodak film. I even experimented with developing photos in the bathroom, though I usually dropped the film off at a Kodak center and received the prints two weeks later, only to discover that some images were out of focus or poorly framed. Today, every smartphone contains a high-quality camera capable of producing stunning images instantly.
Specially Developed for Laser Plastic Welding from LPKF
06/25/2025 | LPKFLPKF introduces TherMoPro, a thermographic analysis system specifically developed for laser plastic welding that transforms thermal data into concrete actionable insights. Through automated capture, evaluation, and interpretation of surface temperature patterns immediately after welding, the system provides unprecedented process transparency that correlates with product joining quality and long-term product stability.
Excellon Installs COBRA Hybrid Laser at Innovative Circuits
06/23/2025 | ExcellonExcellon is pleased to announce the successful installation of a second COBRA Hybrid Laser System at Innovative Circuits, located in Alpharetta, Georgia. The Excellon COBRA Hybrid Laser System uniquely combines both UV and CO₂ (IR) laser sources on a single platform—making it ideal for high-density prototype and production printed circuit boards (PCBs).