- News
- Books
Featured Books
- I-Connect007 Magazine
Latest Issues
Current Issue
Beyond the Rulebook
What happens when the rule book is no longer useful, or worse, was never written in the first place? In today’s fast-moving electronics landscape, we’re increasingly asked to design and build what has no precedent, no proven path, and no tidy checklist to follow. This is where “Design for Invention” begins.
March Madness
From the growing role of AI in design tools to the challenge of managing cumulative tolerances, these articles in this issue examine the technical details, design choices, and manufacturing considerations that determine whether a board works as intended.
Looking Forward to APEX EXPO 2026
I-Connect007 Magazine previews APEX EXPO 2026, covering everything from the show floor to the technical conference. For PCB designers, we move past the dreaded auto-router and spotlight AI design tools that actually matter.
- Articles
- Columns
- Links
- Media kit
||| MENU - I-Connect007 Magazine
Assemblers Play the ‘Revise or Wait’ Game With Designers
June 22, 2022 | Nolan Johnson, I-Connect007Estimated reading time: 2 minutes
Nolan Johnson recently spoke with Duane Benson at Milwaukee Electronics and Screaming Circuits. Duane was pointing out a trend in moving designs into production, which he termed “revise or wait.” This excerpt provides a preview of our exploration of similar topics involving supply chain issues, lead times, and proceeding forward despite the supply challenges.
Nolan Johnson: Duane, the idea of “revise or wait” is interesting. Tell me more.
Duane Benson: It really is. I keep going back to the old “build or buy” idea. See, there are people who say, “I can design that little module much better than someone else can.” But there are also submodules which nobody designs; almost nobody designs their own Bluetooth or Wi-Fi section of their circuit, for example. Instead, you buy a module. You have that decision, though: Are you going to build it, or are you going to buy it?
The “revise or wait” design methodology is very similar except, instead of gambling against your ability to design something better, you’re gambling against the supply chain. We’ve got vendors who are saying some components are out 52 weeks, and then they’re telling us they will be late even to that wait time. We can’t even ask about expedite fees until after those 52 weeks are over. So, what do you do?
Well, perhaps you’ve designed in one of these awesome new little power components that cut the size of your power supply in half; you don’t want to give that up. But is it worth it to wait an extra year before your design makes it to market? Sometimes the redesign will propagate off the board, throughout the system and all the way out to the packaging, but you must make that decision because a significant edge over your competition might be in the balance.
The fun part, of course, comes when the part manufacturer quotes you 52+ weeks, and you go ahead and spend a month redesigning a tiny little bit of the circuit, lay it out again, and get a couple of prototypes made—only to have the original manufacturer surprise you by saying, “Oh, by the way, we happened to get some fab capacity early. So, all those parts that we said you’d never ever be able to get? Here’s a bunch of them.”
That is absolutely the world we live in. Doesn’t matter if we like it or not, that’s where we are right now, and we must be willing to make those kinds of decisions. But trade-offs really are a big part of the stock-in-trade of the engineering world. "Revise or wait" is just another name for what we always do—create great things out of chaos.
I-Connect007 continues to cover industry topics and challenges. Subscribe to SMT007 Magazine, PCB007 Magazine and DESIGN007 Magazine to keep up with the industry conversations.
Testimonial
"Our marketing partnership with I-Connect007 is already delivering. Just a day after our press release went live, we received a direct inquiry about our updated products!"
Rachael Temple - AlltematedSuggested Items
EMAC Returns with Bright Electronics Manufacturing Challenge 2026
04/30/2026 | SMTAThe Electronics Manufacturing & Assembly Collaborative (EMAC) has announced the return of the Bright Electronics Manufacturing Challenge 2026, an immersive, hands-on student competition that puts real electronics manufacturing experience into the hands of the next generation of engineers.
A Designer's Focus on High Density
04/30/2026 | Marcy LaRont, I-Connect007 MagazineVern Solberg is a distinguished member of the Global Electronics Association Raymond E. Pritchard Hall of Fame and has served as chair or vice chair of many committees, developing technical standards and implementation guidelines, including the IPC-7090 series, which focuses on design for manufacturing and reliability for electronic assemblies. He’s a long-time contributor to Design007 Magazine, and he conducted a half-day tutorial at APEX EXPO 2026, where he addressed 2D, 2.5D, and 3D packaging and ultra-high density hybrid bond interconnect. I caught up with Vern at the show and asked about his pivot from addressing more standard design challenges to his focus on high-density circuits.
Zuken Launches GENESYS 2026 to Broaden Access and Improve MBSE Workflows
04/28/2026 | ZukenZuken announced GENESYS 2026, the latest version of its model-based systems engineering platform, with updates designed to improve performance, expand access to model-based information, and enhance the day-to-day modeling experience for engineering teams.
EDADOC: Building the ‘Neural Hub’ for High-Compute Chips Within a Compact Space
04/28/2026 | ECIOEvery chip to the market must pass a stringent checkpoint before shipment known as ATE testing. Serving as the physical “neural hub” that connects test equipment worth millions of dollars with the device under test, the performance of the ATE test board directly determines the accuracy, efficiency, and final yield of chip testing. Amid the rapid rise of high-compute chips, what extreme challenges is this seemingly small circuit board facing? How is EDADOC addressing industry pain points through its one-stop “design + manufacturing” model?
Cadence Reports Q1 2026 Financial Results
04/28/2026 | Cadence Design SystemsCadence had a strong start to 2026, delivering a solid Q1 with accelerating AI demand and record backlog, reflecting strong customer commitment to our AI-driven portfolio,” said Anirudh Devgan, president and chief executive officer.