- News
- Books
Featured Books
- pcb007 Magazine
Latest Issues
Current IssueAdditive Manufacturing
In this month’s issue, we explore additive manufacturing technology for the PCB fabricator: where it stands today, the true benefits, and where it seems to be headed.
The Growing Industry
In this issue of PCB007 Magazine, we talk with leading economic experts, advocacy specialists in Washington, D.C., and PCB company leadership to get a well-rounded picture of what’s happening in the industry today. Don’t miss it.
The Sustainability Issue
Sustainability is one of the most widely used terms in business today, especially for electronics and manufacturing but what does it mean to you? We explore the environmental, business, and economic impacts.
- Articles
- Columns
Search Console
- Links
- Events
||| MENU - pcb007 Magazine
Assemblers Play the ‘Revise or Wait’ Game With Designers
June 22, 2022 | Nolan Johnson, I-Connect007Estimated reading time: 2 minutes
Nolan Johnson recently spoke with Duane Benson at Milwaukee Electronics and Screaming Circuits. Duane was pointing out a trend in moving designs into production, which he termed “revise or wait.” This excerpt provides a preview of our exploration of similar topics involving supply chain issues, lead times, and proceeding forward despite the supply challenges.
Nolan Johnson: Duane, the idea of “revise or wait” is interesting. Tell me more.
Duane Benson: It really is. I keep going back to the old “build or buy” idea. See, there are people who say, “I can design that little module much better than someone else can.” But there are also submodules which nobody designs; almost nobody designs their own Bluetooth or Wi-Fi section of their circuit, for example. Instead, you buy a module. You have that decision, though: Are you going to build it, or are you going to buy it?
The “revise or wait” design methodology is very similar except, instead of gambling against your ability to design something better, you’re gambling against the supply chain. We’ve got vendors who are saying some components are out 52 weeks, and then they’re telling us they will be late even to that wait time. We can’t even ask about expedite fees until after those 52 weeks are over. So, what do you do?
Well, perhaps you’ve designed in one of these awesome new little power components that cut the size of your power supply in half; you don’t want to give that up. But is it worth it to wait an extra year before your design makes it to market? Sometimes the redesign will propagate off the board, throughout the system and all the way out to the packaging, but you must make that decision because a significant edge over your competition might be in the balance.
The fun part, of course, comes when the part manufacturer quotes you 52+ weeks, and you go ahead and spend a month redesigning a tiny little bit of the circuit, lay it out again, and get a couple of prototypes made—only to have the original manufacturer surprise you by saying, “Oh, by the way, we happened to get some fab capacity early. So, all those parts that we said you’d never ever be able to get? Here’s a bunch of them.”
That is absolutely the world we live in. Doesn’t matter if we like it or not, that’s where we are right now, and we must be willing to make those kinds of decisions. But trade-offs really are a big part of the stock-in-trade of the engineering world. "Revise or wait" is just another name for what we always do—create great things out of chaos.
I-Connect007 continues to cover industry topics and challenges. Subscribe to SMT007 Magazine, PCB007 Magazine and DESIGN007 Magazine to keep up with the industry conversations.
Suggested Items
Quantic Electronics Announces Acquisition of M Wave Design
05/20/2024 | Quantic ElectronicsQuantic® Electronics, a portfolio company of Arcline Investment Management, announced the acquisition of M Wave Design, a leading supplier of ferrite-based RF and Microwave components for aerospace, defense, and quantum computing applications.
Textron Systems Collaborates with Kodiak to Develop Uncrewed Military Vehicle
05/20/2024 | PRNewswireTextron Systems Corporation, a Textron Inc. company, a leading developer of crewed and uncrewed military ground vehicles, and Kodiak Robotics, Inc., a leading self-driving technology developer for the trucking and defense markets, announced that they are collaborating to develop an autonomous military ground vehicle specifically designed for driverless operations.
Spring 2024 Santa Clara County Flexfactor Finals Held at Nextflex
05/20/2024 | NextFlexNextFlex hosts this semester’s FlexFactor. Four teams of high school students competed by pitching their inventive products to a panel of esteemed judges composed of Robert de Neve, General Partner & Chief Strategist General Partner & Chief Strategist at NextPhase Ventures; Christine Holly Ngo, VP of Operations and Business Development at Silicon Valley Elite Manufacturing, Inc; and Jackson Rambough, FHE Design and Process Engineer at NextFlex.
Würth Elektronik in United States Embarks on New Milestone with State-of-the-Art Headquarters
05/17/2024 | Wurth ElektronikWürth Elektronik in the United States, a leading manufacturer of electronic and electromechanical components as well as custom magnetics, has announced the commencement of construction on a new 70,000-square-foot headquarters. This new facility underscores the company’s commitment to innovation and grow in the electronics industry.
IPC APEX EXPO: Some Thoughts About Growth
05/16/2024 | Dan Feinberg, I-Connect007After two and a half days of wandering the aisles at IPC APEX EXPO 2024, for the first time, I almost felt like I was exploring CES. There were so many booths and exhibits that I could describe, but I’d like to focus on the growth and huge value of this event, which has expanded well beyond just the growing and impressive exhibit show floor.