Most Comprehensive Analysis of Electricity Reliability Trends
August 25, 2015 | Lawrence Berkeley National LaboratoryEstimated reading time: 2 minutes
In the most comprehensive analysis of electricity reliability trends in the United States, researchers at Lawrence Berkeley National Laboratory (Berkeley Lab) and Stanford University have found that, while, on average, the frequency of power outages has not changed in recent years, the total number of minutes customers are without power each year has been increasing over time.
Reliability-Cover-Final
The researchers pinpointed what utilities and their regulators refer to as “major events,” or events generally related to severe weather, as the principal driver for this trend. “This finding suggests that increasingly severe weather events are linked to a 5-10% increase in the total number of minutes customers are without power each year,” said Berkeley Lab Research Scientist and Stanford PhD candidate, Peter Larsen, the lead author.
The researchers analyzed reports for a large cross-section of utilities representing nearly 70 percent of U.S. electricity customers spanning 13 years from 2000 to 2012. Their report, “Assessing Changes in the Reliability of the U.S. Electric Power System,” is available here.
Although a 2013 White House report noted that major power outages and severe weather events are increasing, this study is the first of its kind to use econometric analysis techniques to statistically correlate these events with electricity reliability. Most studies of reliability have relied on information that reflects only the largest power outages. Yet, over the course of any given year, the largest events typically account for no more than 10 percent of all power outages. This study, by relying on information for all power outages, both large and small, conclusively identifies a trend that is linked directly to these larger events.
One surprise was that the study did not find a consistent link between reliability and utility transmission and distribution (T&D) expenditures. “We expected to find that increased spending on T&D would lead to improved reliability, but it is possible that a combination of proactive versus reactive utility maintenance policies may be off-setting this effect on reliability,” Larsen said. He anticipates that future research will be able sort this out through more detailed analysis of utility spending practices.
Co-author and Berkeley Lab Staff Scientist Joseph Eto said: “We hope the findings from the study will provide a more solid basis upon which to ground future private and public decisions on the long-term reliability of the U.S. electric power system.”
This work was funded by the Office of Electricity Delivery and Energy Reliability, National Electricity Delivery Division of the U.S. Department of Energy. Other co-authors were Kristina H. LaCommare of Berkeley Lab and James L. Sweeney of Stanford.
About Lawrence Berkeley National Laboratory
Lawrence Berkeley National Laboratory addresses the world’s most urgent scientific challenges by advancing sustainable energy, protecting human health, creating new materials, and revealing the origin and fate of the universe. Founded in 1931, Berkeley Lab’s scientific expertise has been recognized with 13 Nobel prizes. The University of California manages Berkeley Lab for the U.S. Department of Energy’s Office of Science.
Suggested Items
Real Time with… IPC APEX EXPO 2024: Innovative Lamination Technology
05/07/2024 | Real Time with...IPC APEX EXPOKevin Barrett of Insulectro and Victor Lazaro of Indubond discuss their companies' partnership, focusing on Indubond's innovative lamination technology that uses induction heating. They discuss the advantages of this technology over traditional methods, its benefits to customers, and the crucial role of automation in manufacturing.
Micron First to Ship Critical Memory for AI Data Centers
05/01/2024 | MicronMicron Technology, Inc. announced it is leading the industry by validating and shipping its high-capacity monolithic 32Gb DRAM die-based 128GB DDR5 RDIMM memory in speeds up to 5,600 MT/s on all leading server platforms.
HQ NextPCB of HQ Electronics Debut on the International Stage for Electronics Manufacture at IPC APEX 2024
05/01/2024 | PRNewswireHQ NextPCB of HQ Electronics, a leading Chinese-based multilayer PCB manufacturer and assembly house showcased its industrial prowess on the international stage for the first time at the IPC APEX Expo 2024.
GPV’s Q1 2024 Interim Financial Report Shows Strong Navigation in Uncertain Times
05/01/2024 | GPVDanish-based GPV recorded an expected drop in sales to DKK 2.3 billion for the first quarter of 2024. The decline also affected the operating profit, which was DKK 155 million compared to DKK 179 million in the same quarter last year, although the EBITDA margin was maintained. In general, demand has been softer in 2024, but GPV continues to invest for the long-term and expects the trend to turn in the second half of 2024.
The Knowledge Base: A CM’s Perspective on Box Build Practices
04/30/2024 | Mike Konrad -- Column: The Knowledge BaseIn the ever-evolving landscape of electronics manufacturing, the box-build process stands out as a critical phase that bridges the gap between individual component manufacturing and the delivery of a fully functional electronic system. This intricate procedure, encompassing the assembly of everything from PCBs to wire harnesses and mechanical enclosures, demands a high level of precision, efficiency, and innovation. As the electronics assembly industry expands and diversifies, understanding the best practices within box-build assembly has become paramount for manufacturers aiming to stay ahead in a competitive market.