- News
- Books
Featured Books
- smt007 Magazine
Latest Issues
Current IssueComing to Terms With AI
In this issue, we examine the profound effect artificial intelligence and machine learning are having on manufacturing and business processes. We follow technology, innovation, and money as automation becomes the new key indicator of growth in our industry.
Box Build
One trend is to add box build and final assembly to your product offering. In this issue, we explore the opportunities and risks of adding system assembly to your service portfolio.
IPC APEX EXPO 2024 Pre-show
This month’s issue devotes its pages to a comprehensive preview of the IPC APEX EXPO 2024 event. Whether your role is technical or business, if you're new-to-the-industry or seasoned veteran, you'll find value throughout this program.
- Articles
- Columns
Search Console
- Links
- Events
||| MENU - smt007 Magazine
Five Issues Troubling EMS Companies
March 21, 2023 | Mark Wolfe, IPCEstimated reading time: 2 minutes
The role of electronics manufacturing services (EMS) companies is very often misunderstood. Some perspectives, however, are helpful in framing the question of what’s on their minds, especially in the current global environment.
EMS companies build products but they are not really “product” companies. While they may provide design services, the designs are still owned by their customers. As a result, they do not have the right to select or change components. In most cases, the EMS company will still be responsible for purchasing these components which are typically 70–90% of their cost to produce the end products. They also do not determine what volumes should be built.
At the same time, they are in an extremely competitive market, with over 1,000 EMS companies in North America alone. Large, publicly-traded EMS companies report gross margins in the high single digits. Smaller and niche EMS companies typically have slightly higher margins but are generally more constrained by working capital availability. In either case, to make this work in a sustainable, profitable manner, they must be able to manage materials and add value to create products as efficiently as possible. They need to convert component inventory to cash; to achieve this, it’s essential to have dependable supply chains and a trained labor force.
Consequences of the Past Two Years
Anyone who has been in the electronics industry for any length of time knows that the past two years have seen an unprecedented combination of labor shortages, supply constraints, demand surges, and global disruptions. In the past, EMS companies and their customers could typically escalate within their established supply chains and reasonably mitigate significant constraints to a manageable level. This has not been the case over the past couple of years. Trusting that the original part from the established supply chain would ultimately be available with enough effort and leverage has just not worked.
As a result, EMS companies have been forced to push component issues back to their customers more often than ever before. When the parts are available in secondary markets or from brokers, they are viewed as having higher counterfeit risks and are often at extremely high relative costs. If the secondary market is not an option, the burden typically falls on the customer to explore alternate designs. These are usually last resorts and can create high-risk product transitions. Ultimately, all these issues are pushed back to customers for risk signoff and financial support, or an EMS company may not be able to survive the financial consequences.
The availability of a trained workforce, especially on the production floor, has also been challenging, especially as demand has grown. When parts are available, many EMS companies have not had enough wage workforce available to recover quickly.
The result? Even the most historically efficient EMS operations are being continuously disrupted and too many materials are occupying space, if not cash. Customer relationships, cash flow, and EMS profits have all been under duress.
To continue reading this article where Mark outlines the five issues plaguing EMS companies, click here or download your copy of the March issue of SMT007 Magazine.
Suggested Items
Micron First to Ship Critical Memory for AI Data Centers
05/01/2024 | MicronMicron Technology, Inc. announced it is leading the industry by validating and shipping its high-capacity monolithic 32Gb DRAM die-based 128GB DDR5 RDIMM memory in speeds up to 5,600 MT/s on all leading server platforms.
HQ NextPCB of HQ Electronics Debut on the International Stage for Electronics Manufacture at IPC APEX 2024
05/01/2024 | PRNewswireHQ NextPCB of HQ Electronics, a leading Chinese-based multilayer PCB manufacturer and assembly house showcased its industrial prowess on the international stage for the first time at the IPC APEX Expo 2024.
GPV’s Q1 2024 Interim Financial Report Shows Strong Navigation in Uncertain Times
05/01/2024 | GPVDanish-based GPV recorded an expected drop in sales to DKK 2.3 billion for the first quarter of 2024. The decline also affected the operating profit, which was DKK 155 million compared to DKK 179 million in the same quarter last year, although the EBITDA margin was maintained. In general, demand has been softer in 2024, but GPV continues to invest for the long-term and expects the trend to turn in the second half of 2024.
The Knowledge Base: A CM’s Perspective on Box Build Practices
04/30/2024 | Mike Konrad -- Column: The Knowledge BaseIn the ever-evolving landscape of electronics manufacturing, the box-build process stands out as a critical phase that bridges the gap between individual component manufacturing and the delivery of a fully functional electronic system. This intricate procedure, encompassing the assembly of everything from PCBs to wire harnesses and mechanical enclosures, demands a high level of precision, efficiency, and innovation. As the electronics assembly industry expands and diversifies, understanding the best practices within box-build assembly has become paramount for manufacturers aiming to stay ahead in a competitive market.
I-Connect007 Editor’s Choice: Five Must-Reads for the Week
04/26/2024 | Andy Shaughnessy, Design007 MagazineIn this week’s roundup, we have a variety of articles covering everything from design through assembly, and even box build. I’ve always wondered whether box build was all it was cracked up to be. Do customers really pick one EMS provider over another because one company offers box build? And if you’ve ever wanted to volunteer, IPC’s Thought Leaders Program is looking for a few good technologists to help them on their mission. Check out Stanton Rak’s article, which was published in the spring issue of IPC Community.