- News
- Books
Featured Books
- smt007 Magazine
Latest Issues
Current IssueWhat's Your Sweet Spot?
Are you in a niche that’s growing or shrinking? Is it time to reassess and refocus? We spotlight companies thriving by redefining or reinforcing their niche. What are their insights?
Moving Forward With Confidence
In this issue, we focus on sales and quoting, workforce training, new IPC leadership in the U.S. and Canada, the effects of tariffs, CFX standards, and much more—all designed to provide perspective as you move through the cloud bank of today's shifting economic market.
Intelligent Test and Inspection
Are you ready to explore the cutting-edge advancements shaping the electronics manufacturing industry? The May 2025 issue of SMT007 Magazine is packed with insights, innovations, and expert perspectives that you won’t want to miss.
- Articles
- Columns
- Links
- Media kit
||| MENU - smt007 Magazine
Supply Chain Update and the Impact of 5G
December 4, 2019 | Nolan Johnson, I-Connect007Estimated reading time: 2 minutes

I caught up with Stephanie Martin, senior VP of global supply at Vexos, to talk about the current landscape of the industry from an EMS perspective. Stephanie describes an ongoing technology shift occurring with the industry’s move to smaller case sizes and why it’s in the customer’s best interest to look at the design cycle and go as small as they can on components.
Nolan Johnson: Stephanie, you were so helpful earlier this year when we discussed parts shortages; you gave some great global insight. What has changed in the industry?
Stephanie Martin: This year has had significant changes. Last year through December of 2018, we were in the supercycle with shortages and extremely long lead times. MLCCs were out for 52 weeks, and several suppliers did not even accept orders. They were in that tight of supply, so everything was fully allocated, and we had that across a number of components. Lead times extended, and prices rose; it was a pretty bad situation. I’ve been in electronics for over 20 years, and it was the worst situation from a buying perspective I have ever seen.
Starting in January of 2019, things started to ease up. We first caught wind of some easing up in Asia in late Q4 and early Q1 this year. The distributors in Asia told me their business was down 8% in Q4, and then an additional 10% in Q1 of this year. In their opinion, this was primarily driven by a reduction in the automotive industry in Chinese manufacturing and a reduction in the number of cellphones being built. As a result, that eased up a lot of material. By the end of Q1 of this year, we saw available supply in most commodities. Prices have been dropping and stabilizing. Lead times are down to what we would consider being near normal, which is somewhere in the 10–12-week range for most components as opposed to 30+ weeks last year.
However, some spotty problems can still happen. We’re still struggling with MOSFETs, which are still in the 30+ week range. I don’t see any real change in that happening yet, but most of the other components—particularly the MLCCs and smaller sizes, such as 0201s and some 0402s—are down to reasonable lead times. The larger case sizes for the MLCCs are still constrained, of which the sizes 0603, 0805, and 1206 are the most common; those still have longer lead times with 25 weeks or more, and we do not expect to see them improve at all.
To read this entire interview, which appeared in the November 2019 issue of SMT007 Magazine, click here.
Suggested Items
It’s Only Common Sense: Why Sales Teams Fail (and How to Fix Them)
06/22/2025 | Dan Beaulieu -- Column: It's Only Common SenseIn sales, success is never a given. Despite best intentions, the most well-resourced sales teams can stumble. Understanding why is the first step toward creating a high-performing sales force. Here are the main reasons sales teams fail—and actionable strategies to fix them.
STI Celebrates Travis Wease’s 10 Years of Dedicated Service
06/17/2025 | STI Electronics, Inc.STI Electronics, Inc., a full-service organization providing training services, training materials, analytical/failure analysis, prototyping, and contract electronic manufacturing, proudly celebrated the 10-year work anniversary of Travis Wease, Master Instructor and valued team member.
The Marketing Minute: A Brand Visibility Playbook—Get Seen, Heard, and Remembered
06/18/2025 | Brittany Martin -- Column: The Marketing MinuteIn the competitive world of electronics, recognition isn’t given—it’s earned. With so many companies vying for attention, how do you ensure your brand voice stands out and stays top-of-mind? This month, I’m focusing on building recognition using three high-impact tools: social media, paid advertising, and thought leadership.
The Government Circuit: From Tax Policy to Tariffs, Denver to Delhi, Speaking Up for Electronics
06/18/2025 | Chris Mitchell -- Column: The Government CircuitI had the privilege of attending the June 3 opening ceremony of AT&S’s HTB3 facility in Leoben, Austria—a milestone moment for Europe’s electronics ecosystem. HTB3 is now the first and only facility in Europe capable of both developing and producing high-performance IC substrates—the advanced platforms that allow powerful chips to connect, process, and function. As demand for AI, 5G, and other cutting-edge technologies grows, so too does the need for sophisticated substrates like those HTB3 will produce.
I-Connect007 Editor’s Choice: Five Must-Reads for the Week
06/13/2025 | Marcy LaRont, I-Connect007Today is Friday the 13th, and in much of Western folklore, this is a day when bad luck is lurking. But while Friday the 13th may top Western superstition charts, the global calendar is sprinkled with its own unlucky legends. In Spain and Greece, the bad juju lands on Tuesday the 13th—a day linked to Mars, the god of war, and naturally, chaos. In Italy, it’s Friday the 17th that is feared, thanks to the Roman numeral XVII, which can be rearranged to spell VIXI—Latin for “I have lived” (a poetic way of saying you’re dead).