- News
- Books
Featured Books
- pcb007 Magazine
Latest Issues
Current IssueVoices of the Industry
We take the pulse of the PCB industry by sharing insights from leading fabricators and suppliers in this month's issue. We've gathered their thoughts on the new U.S. administration, spending, the war in Ukraine, and their most pressing needs. It’s an eye-opening and enlightening look behind the curtain.
The Essential Guide to Surface Finishes
We go back to basics this month with a recount of a little history, and look forward to addressing the many challenges that high density, high frequency, adhesion, SI, and corrosion concerns for harsh environments bring to the fore. We compare and contrast surface finishes by type and application, take a hard look at the many iterations of gold plating, and address palladium as a surface finish.
It's Show Time!
In this month’s issue of PCB007 Magazine we reimagine the possibilities featuring stories all about IPC APEX EXPO 2025—covering what to look forward to, and what you don’t want to miss.
- Articles
- Columns
Search Console
- Links
- Media kit
||| MENU - pcb007 Magazine
Happy’s Essential Skills: Engineering Economics (ROI)
August 10, 2016 | Happy HoldenEstimated reading time: 7 minutes

Engineering economics is fundamental in engineering, especially for manufacturing support. For simplicity, I am using the term here as a process engineer for printed circuit equipment and automation of production. Principles of Engineering Economy[1], written by Stanford University Professor Dr. Grant Ireson, is the text that I used and one of the basics for understanding engineering economics.
Interest Variables
Here are the five primary variables that make up all of the interest formulas for the time value of money:
I = interest rate per period
n = number of interest periods
PV = present sum of money
FV = future sum of money after n periods at i interest
PMT = end of period payment
All of these calculations lend themselves for use in spreadsheets and are found as part of MS Excel.
Interest Formulas
The interest formulas for these calculations are defined and seen below. For some reason, each of these formulas have been given a specific name and abbreviation. Single amounts do not have an apostrophe after the three-letter-acronym (tla). A series of amounts have the apostrophe (‘). The short-cut way of writing this out is to use this form:
(tla-interest rate-period) seen as: (caf’-6%-10)
- Single Payment-Compound Amount Factor (caf’) for future value (FV) based on the present value (PV):
FV=PV(1+i)^n (caf')
- Single Payment-Present Worth Factor (pwf’) for present value (PV) based on the FV
PV=FV[1/(1+i)^n] (pwf')
- Series Sinking fund factor (sff) for series payment (PMT) based on the FV
PMT=FV[i/(1+i)^n-1] (sff)
- Series Compound Recovery Factor (crf) for series payment (PMT) based on the PV
PMT=PV[i(1+i)^n/(1+i)^n-1] (crf)
or PMT=PV[i/{(1+i)^n-1}+i]
- Series Compound Amount Factor (caf) for future value based on the payments
FV=PMT[(1+i)^n-1/i] (caf)
- Series Present Worth Factor (pwf) for PV based on the series of payments
PV=PMT[(1+i)^n-1/i(1+i)^n] (pwf)
Or PV=PMT[1/{i/(1+i)^n-1}+i]
Examples using Three Variables
You can see how all of these financial formulas are related by looking at the examples in Figure 1. We start with just three variables: present value (PV) = $1000; period of 10 years (N); and annual interest rate of 6%.
1. We start with $1000 (PV) and want to know what it is worth after 10 years with an interest rate of 6% per year. The caf’ equation is used: (caf’-6%-10). The future value (FV) is $1791.
2. What if we want to know what the FV would be if we withdraw it six years early? The pwf’ is used: (pwf’-6%-6) and the PV is $1263.
3. What PV would it take seven years earlier to get this $1263? Again, pwf’ is used: (pwf’-6%-7) and a PV of $840 would be required.
4. If we took the $840 and invested it over 10 years what payments would we receive at 6% interest? The crf is used (crf-6%-10) to get a payment (PMT) of $114/period.
5. If instead we made payments of $114 per period for 10 years, what would that be worth now? The caf equation is used (caf-6%-10) and the future value (FV) is $1504.
6. What annual payment is required to get $1504 over seven years? The sff equation is used (sff-6%-7) and PMT would be $179/ year.
7. What present value would $179 in interest income at 6% give us over seven years? The pwf is used (pwf-6%-7) and the V is $1000, the same as we started with.
Figure 1: Seven financial calculations all involving $1000 at 6% interest over various years.
Important Engineering Metrics
- ROI (return on investment) is the equivalent bank interest rate of all the money you spent and all the profits you made over a fixed time span
- NPV (net present value) is the current value of all the cash flows over time assuming cash is worth, x %, say 3 % as an interest rate.
- BET is the breakeven time (or the time to money) before the profits you gain pay for all that you spent to get the profits. Or, how long before you truly make a PROFIT?
- TVM is the time value of money. Because of inflation, future money is worth less than current money, or it is discounted.
- DEPRECIATION is the value of equipment that the government lets you deduct each year as equipment gets older. This encourages you to buy new equipment. Some may be depreciated very fast, perhaps in three years instead of five.
The common practice in equipment justification is to calculate the ROI or the NPV of the cash flows associated with implementing the equipment, including all purchases of equipment, installation, taxes (depreciation), water treatment savings and operating costs against the labor saving, and yield improvement by NOT installing automation.
The rate of return is easiest calculated by Excel. To do it manually requires a trial-and-error calculation of assuming an interest rate (I) over the period of the investment (n) and calculating the compound recovery factors (crf) for each year. When the sum of all the crfs equals the initial investment, then the interest rate is the ROI.
The NPV is easier to calculate. It is the present worth factor (pwf) for all the cash flows each year for the life of the investment using current or future interest rates.
The classical trade-off is between the purchase of an automated system (and its advantages) and the continued increase in direct labor. But quality, process yields and waste water treatment costs also enter into the calculation. Return on investment is the calculation of the equivalent interest rate of all the moneys invested based on all the cash flows over the useful life of the equipment.
Page 1 of 2
Suggested Items
Elephantech: For a Greener Tomorrow
04/16/2025 | Marcy LaRont, PCB007 MagazineNobuhiko Okamoto is the global sales and marketing manager for Elephantech Inc., a Japanese startup with a vision to make electronics more sustainable. The company is developing a metal inkjet technology that can print directly on the substrate and then give it a copper thickness by plating. In this interview, he discusses this novel technology's environmental advantages, as well as its potential benefits for the PCB manufacturing and semiconductor packaging segments.
Trouble in Your Tank: Organic Addition Agents in Electrolytic Copper Plating
04/15/2025 | Michael Carano -- Column: Trouble in Your TankThere are numerous factors at play in the science of electroplating or, as most often called, electrolytic plating. One critical element is the use of organic addition agents and their role in copper plating. The function and use of these chemical compounds will be explored in more detail.
IDTechEx Highlights Recyclable Materials for PCBs
04/10/2025 | IDTechExConventional printed circuit board (PCB) manufacturing is wasteful, harmful to the environment and energy intensive. This can be mitigated by the implementation of new recyclable materials and technologies, which have the potential to revolutionize electronics manufacturing.
Connect the Dots: Stop Killing Your Yield—The Hidden Cost of Design Oversights
04/03/2025 | Matt Stevenson -- Column: Connect the DotsI’ve been in this industry long enough to recognize red flags in PCB designs. When designers send over PCBs that look great on the computer screen but have hidden flaws, it can lead to manufacturing problems. I have seen this happen too often: manufacturing delays, yield losses, and designers asking, “Why didn’t anyone tell me sooner?” Here’s the thing: Minor design improvements can greatly impact manufacturing yield, and design oversights can lead to expensive bottlenecks. Here’s how to find the hidden flaws in a design and avoid disaster.
Real Time with... IPC APEX EXPO 2025: Tariffs and Supply Chains in U.S. Electronics Manufacturing
04/01/2025 | Real Time with...IPC APEX EXPOChris Mitchell, VP of Global Government Relations for IPC, discusses IPC's concerns about tariffs on copper and their impact on U.S. electronics manufacturing. He emphasizes the complexity of supply chains and the need for policymakers to understand their effects.